Cross-connect
A cross-connect links two networks hosted in the same data centre directly, without going over the Internet. It is a cable, run from panel to panel, but it often carries a customer’s most critical traffic: carrier access, a link to a cloud, the backup route.
From order to live link
- Step 1Order
The customer orders the cross-connect from the data centre operator. The other party provides a LOA (letter of authorisation) naming its panel and port.
- Step 2Install
The link runs from the customer’s panel to the meet-me room or the room’s distribution frame, then to the other party’s panel. The route is planned, not improvised.
- Step 3Sign off
Connectors inspected and cleaned at both ends, testing to specification (optical loss testing, OTDR), label at each end, report with photos of your rack, in line with the site’s photo policy.

What distinguishes one cross-connect from another
- The medium
Single-mode fibre most often, multimode for short distances, copper for certain services.
- Simplex or duplex
One fibre, or two (transmit and receive).
- Connectors
LC and SC most often, MPO for multi-fibre links.
- The route
Within the same room, between two rooms, or between two buildings on the same campus.
Why the backup link matters
A serious customer orders two cross-connects, on two separate routes, and, where the site allows it, through two meet-me rooms. But redundancy protects against one failure, not two. A backup link that is never used can degrade without anyone noticing: a dirty connector drops packets, the link holds, then fails on the day all the traffic switches over to it. It is inspected like the primary link.
In the data centre
Installing patch cords from panel to panel, in the meet-me room and between racks, inspecting and cleaning connectors, testing and labelling: this is our daily work in Île-de-France data centres. Every intervention, however short, is followed by a documented report, with photos of your rack, in line with the site’s photo policy.
Content written by the Full Connection field team and approved by Karim Bouacida, head of the company.
Frequently asked questions
What is the difference between a cross-connect and a patch cord?
The patch cord is the cord. The cross-connect is the complete link between two customers: often several sections, with panels and patch cords at each end.
What is a LOA?
The letter of authorisation, or LOA-CFA, by which one party authorises connection to its panel and states the port to use. Without it, the operator will not install.
Who installs a cross-connect?
On most colocation campuses, the operator installs it with its own teams or contractors. Patching from the customer’s panel to its equipment is the responsibility of the customer or its contractor.
What is a meet-me room?
The data centre’s interconnection room, where carriers and customers have their panels and where cross-connects meet.
Cross-connects to patch or rework?
Describe the site, the maintenance window and the objective.
By phone: 07 76 31 97 87